Major Infrastructure Improvement Projects Completed in 2018-19
Fair Oaks 40” Transmission Pipeline Relining Project (Wholesale)
Beginning in October 2018 and continuing into Spring 2019, San Juan Water District will be relining a 40-inch diameter Transmission Main known as the Fair Oaks-40 (FO-40). The FO-40 Pipeline delivers water to San Juan Water District customers within our Retail Service Area between Oak Avenue to Main and Pershing Avenues. The transmission pipeline also has Wholesale connections to Orange Vale Water Company and is one of two supply connections to Fair Oaks Water District.
The Relining Project is the final phase of a seven year rehabilitation project for this 60 year old pipeline. This final phase of the project includes removing the interior mortar lining and replacing it with a new thicker lining to protect the pipeline from interior corrosion. To complete this work, access points along the pipeline are needed for the crews to remove old lining materials and complete the relining process. Due to the alignment of the project through open fields, back yards and under roadways, close coordination with our customers is key to the success of this project.
Customers will not be out of service during the project; however, the project will create some noise in areas where work is taking place. The project Team has been working with our customers along the pipeline alignment for over a year to coordinate access and the completion of work. Our customers continue to amaze us as to their understanding of the criticality of the project and their willingness to work with their water District to complete this project.
Edward Court Pipeline Replacement (Retail)
This project involves the installation of approximately 300 lineal feet of new 8-in and 4-in C900 PVC pipeline, and the replacement of three (3) services on Edward Ct, south of Lou Place. This project is scheduled to begin between March and June 2019 and should be completed by July or August 2019. Affected customers will be contacted by District personnel a few weeks in advance of the project construction start-up, and will be provided with specific information related to the construction schedule and aspects of the project that may be anticipated to affect our customers.
Lou Place Pipeline Replacement (Retail)
The Lou Place Pipeline Replacement Project will replace approximately 460 lineal feet of existing, aged pipeline, and the existing aged water services. This project replaces old facilities that have reached the end of their useful life, and adds dependability to the water distribution system. This project is scheduled to begin between March and June 2019 and should be completed by July or August 2019. Affected customers will be contacted by District personnel a few weeks in advance of the project construction start-up, and will be provided with specific information related to the construction schedule and aspects of the project that may be anticipated to affect our customers.
Redbud/Lupin/Meadowlark Services Replacements (Retail)
This project involves the replacement of 43 existing, aged water services from the water main in the street to the meter box in the frontage of the yards. The project location is on Redbud Road, Lupin Lane, and Meadowlark Lane, in Granite Bay. This project is scheduled to begin between March and June 2019 and should be completed by July or August 2019. Affected customers will be contacted by District personnel a few weeks in advance of the project construction start-up, and will be provided with specific information related to the construction schedule and aspects of the project that may be anticipated to affect our customers.
Sandstone & Auberry to Hill Rd Pipeline Extension and Services Replacements (Retail)
The Sandstone & Auberry to Hill Road Project involves the replacement of approximately 175 lineal feet of existing, aged 8-in pipeline and 17 water service that have reached the end of their useful lifespan. This project is scheduled to begin between March and June 2019 and should be completed by July or August 2019. Affected customers will be contacted by District personnel a few weeks in advance of the project construction start-up, and will be provided with specific information related to the construction schedule and aspects of the project that may be anticipated to affect our customers.
Douglas Boulevard Pipeline Replacement Project (Retail)
This project consisted of the replacement of an aged water pipeline in Douglas Blvd. between the intersections of Auburn Folsom Road and Mooney Road. The project included the replacement of an old 10-inch steel main, and 23 service connections.
Dambacher Drive Service Replacements Project (Retail)
This project consisted of the installation (replacement) of nineteen (19) aged residential water services along Dambacher Drive. Included in this work was the replacement of eight (8) “Long-Side” and eleven (11) “Short-Side” water services between the existing water main in the street and the water meter boxes along the frontages of each parcel served.